| Activity | Unit | Total Qty | Completed This Period | Cumulative Completed | % Complete | |----------|------|-----------|----------------------|----------------------|-------------| | Chilled water pipe installation (floor 2–3) | LF | 2,500 | 300 | 1,800 | 72% | | Ductwork fabrication & installation (floor 4) | LF | 1,200 | 450 | 450 | 37.5% | | AHU installation (units 1–4) | No. | 4 | 0 | 2 | 50% | | Duct insulation (floor 1) | SF | 8,000 | 2,000 | 8,000 | 100% |
Remarks:
| Trade | Priority | Planned Activities | | :--- | :--- | :--- | | Mech | High | Start VRF piping if units arrive. Complete Level 5 FAHU wiring. | | Electrical | High | Start pulling conductors for Levels 1-2. Install Light fixtures Level 3. | | Plumbing | Medium | Complete Roof RWP. Start Level 5 restroom rough-in. | | All | Critical | Clash resolution meeting for Level 6 ceiling space (Wed 8 AM). | mep work progress report sample
While the sample above is comprehensive, you must tailor it to your project's complexity: | Activity | Unit | Total Qty |